Site icon

SSM Habitat Restoration: McGlinn Island Causeway

Habitat Restoration Feasibility Assessment

Skagit River System Cooperative, 2009 – 2011

Project site: McGlinn Island jetty – North Fork Skagit River

Dredging of the Swinomish Channel began in the1890s to provide a navigation channel between Skagit Bay and Padilla Bay to facilitate commerce. Dredge spoils were used to build a causeway between LaConnor and McGlinn Island to prevent transport of sediments from entering the channel via Dunlop Bay. A jetty was built in 1938 to train the river away from the navigation channel, which further restricted connectivity between the river and the Swinomish Channel. The causeway and jetty have restricted juvenile salmonid access to prominent rearing habitat available in Padilla Bay and reduced freshwater input to the channel. This has greatly increased channel salinity and created a physiological barrier for juvenile Chinook salmon, which are very sensitive to high salinity. Restoring river-channel connectivity is necessary to allow juvenile salmon access to rearing habitat in Padilla Bay.
The overall objective of the McGlinn Island Causeway Feasibility study was to evaluate the potential of restoring historical connectivity between the North Fork Skagit River and the Swinomish Channel connecting Skagit and Padilla Bays. The objective of the associated PNNL modeling task was to conduct hydrodynamic simulation of the proposed restoration alternatives to assess whether expected benefits such as creation of brackish environment and desired level of connectivity for downstream fish migration could be achieved.
A closeup of model grid near McGlinn Island jetty – Skagit River.

The hydrodynamic model of Skagit Bay, Swinomish Channel, and Padilla Bay was refined to include small-scale geometric features associated with the existing river training structures at the site, including the jetties and the dikes. The model reproduced the existing hydrodynamic condition and is being used to evaluate two alternative restoration concepts. Concept 1 involves lowering a river training jetty from McGlinn Island across the river channel. Concept 2 consists of creating a causeway and a dredged channel connecting the North Fork of the Skagit River to Swinomish Channel through Dunlop Bay.

Project Highlights

Contacts and Project Team

Tarang Khangaonkar (CO-PI), Salish Sea Modeling Center
Zhaoqing Yang (CO-PI), PNNL
Steve Hinton (PI), Skagit River System Cooperative

Publications

Yang Z and T Khangaonkar. 2007. Hydrodynamic Modeling Analysis for McGlinn Island Causeway Feasibility Study. PNWD-3813, prepared for the Skagit River System Cooperative, by Battelle, Pacific Northwest Division, Richland, WA.
SRSC, Battelle PNNL, USGS. 2008. McGlinn Island Causeway & Jetty Habitat Restoration Feasibility Phase 1: Establishing the viability of hydraulic connectivity between Skagit and Padilla Bays. Skagit River System Cooperative, Laconnor, WA.

Exit mobile version